Cruise Control Module: Testing and Inspection
SRS components are located in this area. Review the SRS component locations, precautions, and procedures in the SRS section before performing repairs or service.Remove the bulkhead panel, then disconnect the connectors from the ECM and make the following tests.
Inspect the connector and socket terminals to be sure they are all making good contact.
^ If the terminals are bent, loose, or corroded, repair them as necessary, and recheck the system.
Control Unit Input Test:
Control Unit Input Test:
^ If the terminals look OK, make the following input tests at the connector.
- If any test indicates a problem, find and correct the cause, then recheck the system.
- If all the input tests prove OK, the ECM must be faulty; replace it.