Operation CHARM: Car repair manuals for everyone.

Shift Interlock Switch: Testing and Inspection




Park Pin Switch Test

1. Remove the center console panel Center Console Panel Removal / Installation.

2. Disconnect the 6P connector (A) from the A/T shift lock solenoid/park pin switch/A/T gear position indicator panel light connector (B).






3. Check for continuity between the terminals in each switch position according to the table.





4. If the continuity is not as specified, check the shift cable adjustment Adjustments. If the cable adjustment is OK, replace the park pin switch Shift Lock Solenoid Test.