Cylinder Head, Removing
Cylinder Head, Removing
Special tools, testers and auxiliary items required
• Lifting Tackle (3033)
• Shop Crane (VAS 6100)
Procedure
• Engine installed.
• All cable ties which are opened or cut open when removing, must be replaced in the same position when installing.
• Heat shield boots that were removed should be installed in the same location during installation.
• Perform oil change if engine oil is contaminated.
- Drain the coolant. Refer to => [ Cooling System, Draining and Filling ] Procedures.
- Remove the intake manifold.
- Remove coolant hoses to heater core on bulkhead - arrows -.
- Disconnect following hose connections:
1. Coolant hose to reservoir
2. Vacuum hose to Evaporative Emission (EVAP) Canister
3. Vacuum hose to Leak Detection Pump
4. Fuel supply line
5. Coolant hose to reservoir
- Disconnect coolant hoses at positions indicated by - arrows -.
• Ignore - 1 -.
• Shown in illustration on vehicle with Direct Shift Gearbox transmission.
- Remove wiring connections with coolant and vacuum hoses.
- Remove camshaft timing chain from camshafts. Refer to => [ Camshaft Timing Chain ] Camshaft Timing Chain.
• Do not bend the flex joints in front of the exhaust pipe more than 30° or they may be damaged.
- Remove front exhaust pipe from exhaust manifolds - arrows -.
- Loosen and remove cylinder head bolts in sequence shown.
- Engage (3033) as follows:
• Belt pulley side: Position - 3 -.
• Timing chain side: Position - 10 -.
• (3033) positions marked with 1 to 12 face toward timing chain side.
- Carefully raise cylinder head.
- Place clean cloth in cylinder so that no dirt can enter between cylinder wall and pistons.