Operation CHARM: Car repair manuals for everyone.

Supercharger: Testing and Inspection






Supercharger, Checking for Leaks

Special tools, testers and auxiliary items required

Testing Unit for Turbocharger (V.A.G 1687) with Adapter (V.A.G 1687/10) (V.A.G 1687/13-1) , (V.A.G 1687/13-2) and (V.A.G 1687/13-3)

Engine and Transmission Holder (VAS 6095)

Ultrasonic Measuring Device (V.A.G 1842)

Procedure

Secure the supercharger to the (VAS 6095) when performing the leakage test. Refer to => [ Supercharger, Securing to Engine and Transmission Holder ] Supercharger, Securing to Engine and Transmission Holder.

Control valve control unit (J808) installed.

- Attach the (V.A.G 1687/13-1) to the bottom of the supercharger housing.






- Secure the hose connections with hose clamps.

The supercharger is illustrated without the transmission holder.

- Attach the (V.A.G 1687/13-3) to the top of the supercharger housing.






- Secure the hose connections with hose clamps.

- Attach the (V.A.G 1687/13-2) and (V.A.G 1687/10) to the supercharger housing.






- Secure the hose connections with hose clamps.

Prepare the (V.A.G 1687) as follows:






- Remove the pressure regulator valve - 2 - and close valves - 3 - and - 4 -.

Pull the knob in order to rotate the pressure regulating valve.

- Connect the (V.A.G 1687) as illustrated, to the compressed air using a commercially available intermediate piece - 1 -.






- If there is water in the viewing glass, open the water drain plug - 6 - and drain the water.






- Open the valve - 3 -.


Damage could result if the pressure is set too high.

Pressure must not exceed 0.5 bar!

- Set the pressure to 0.5 bar using the pressure control valve - 2 -.

- Open the valve - 4 - and wait until the test circuit is filled. Regulate the pressure to 0.5 bar again if necessary.

- Closes the valve - 3 -.

The drop in pressure must not exceed 0.1 bar in 30 seconds.

- Inspect the charge air system for poorly sealed areas by listening, feeling, using commercially available leak detection spray or by using the (V.A.G 1842).

For information on using the (V.A.G 1842) the operating Instructions.

Release the pressure in the test circuit by pulling off the hose coupling before removing the adapter.