Operation CHARM: Car repair manuals for everyone.

Programming and Relearning



61 35 ... Vehicle Programming And Coding







NOTE:
- In order to avoid incorrect programming procedures and error messages, it is essential when working with the ISTA/P programming system always to use the version.
- Battery voltage must not drop below 13.0 V during programming. Connect battery charger prior to programming
Use only BMW-recommended battery chargers*
*Sourcing reference Workshop Equipment Catalogue







Programming sequence via ISTA/P:
- Identify vehicle and read out control unit data
- Draw up and configure measures plan
- Prepare programming, export CBS/CKM data
- Carry out repair measures, replace control units if necessary
- Identify vehicle again after repair. Update measures plan
- Carry out programming
- Assess programming afterwards, import CBS/CKM data
- Programming successfully completed