Piston Ring: Labor Times

Standard HoursManufacturer Warranty HoursSkill LevelNotes
Replace
One CYL
Right Bank11.27.7AIncludes: R&R Cylinder Head & Oil Pan, Hone Cylinder Walls And Plastigage Bearings.
Left Bank11.37.8AIncludes: R&R Cylinder Head & Oil Pan, Hone Cylinder Walls And Plastigage Bearings.
Both Banks13.59.5AIncludes: R&R Cylinder Head & Oil Pan, Hone Cylinder Walls And Plastigage Bearings.
All CYL
Right Bank12.48.9AIncludes: R&R Cylinder Head & Oil Pan, Hone Cylinder Walls And Plastigage Bearings.
Left Bank12.59.0AIncludes: R&R Cylinder Head & Oil Pan, Hone Cylinder Walls And Plastigage Bearings.
Both Banks17.911.9AIncludes: R&R Cylinder Head & Oil Pan, Hone Cylinder Walls And Plastigage Bearings.