Standard HoursManufacturer Warranty HoursSkill LevelNotes
Resurface/Grind
Right Bank11.07.6AIncludes: R&R Cylinder Head And Make All Necessary Adjustments.
Left Bank10.47.2AIncludes: R&R Cylinder Head And Make All Necessary Adjustments.
Both Banks15.410.4AIncludes: R&R Cylinder Head And Make All Necessary Adjustments.
Add the Following Operations If Performed With Valves, Grind
Valve Guides, Knurl
Each0.30.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Tune-Up0.70.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Timing Chain, Renew1.80.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Valve Lifters, Renew2.40.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Camshaft, Renew5.10.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Rocker Arm or Stud, Renew
Each0.20.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Valves Guides, Renew
Each0.20.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.
Note
To Ream Guide, Add0.10.0AAdd Any Of The Following Operations If Performed Along With Valves, Grind.