| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
Replace |
Complete Assembly With Transfer of Parts | 12.0 | 7.5 | B | Includes: Transfer All Fuel And Electrical Units. Does Not Include: Transfer Of Any Optional Equipment. |
Note |
With Heavy Duty Cooling, Add | 0.8 | 0.5 | B | |
Complete Assembly Without Transfer of Parts | 10.0 | 0.0 | B | Does Not Include: Transfer Of Any Part Of Engine Or Replacement Of Optional Equipment. |
Long Block | 17.7 | 0.0 | A | Includes: R&I Engine And Transfer All Necessary Components Not Supplied With Long Block. |
Short Block | 19.5 | 12.7 | A | Includes: R&R Engine And Replacement Of All Necessary Components. |
Note |
To Grind All Valves, Add | 3.8 | 2.7 | A | |
With Heavy Duty Cooling, Add | 0.8 | 0.5 | A | |
Overhaul/Rebuild | 34.0 | 0.0 | A | Includes: Disassemble & Clean Engine. Ridge Ream & Hone Cylinders. Fit Pistons, Rings, Pins, Main & Rod Bearings. Grind Valves & Tune-Up. |