Operation CHARM: Car repair manuals for everyone.

Assembly Procedure

Starter Motor Overhaul: Disassembly Procedure:




1. Install the magnets (1) in the housing:
^ Use a soft drift in order to seat the magnets in the housing.
^ Install the retainer.

Starter Motor Overhaul: Disassembly Procedure:




2. Install the gear reduction unit shield to the housing.

Starter Motor Overhaul: Disassembly Procedure:




3. Carefully pry apart the shift lever legs (4) in order to install the lever to the drive gear.
4. Install the drive gear (3) and the retainer collar to the gear reduction unit.
5. Install the drive gear retainer.
6. Snap the drive gear retainer collar onto the retainer using a plastic tool.

Starter Motor Overhaul: Disassembly Procedure:




7. Install the brush holder plate (2) using a piece of pipe or a socket (1) about 320 mm (1.25 in) in order to retain the brushes.

Starter Motor Overhaul: Disassembly Procedure:




8. Install the following components to the armature:
^ The thrust washer (2)
^ The shield (3)
^ The seal (4)
^ The washer (5)

Starter Motor Overhaul: Disassembly Procedure:




9. Install the armature C clip (3).
10. Install the bearing housing (1).
11. Install the bearing housing screws (2).
Tighten
Tighten the screws to 1.8 N.m (16 lb in).

Starter Motor Overhaul: Disassembly Procedure:




12. Lightly tap the brush holder (1) I order to seat in the housing and to install the armature with the holder.

Starter Motor Overhaul: Disassembly Procedure:




13. Push in the drive pinion with the ear reduction unit.
14 Install the drive pinion housing.
15. Push the shift lever guide into the drive pinion housing.
16. Install the shift lever plunger to the solenoid housing.

Starter Motor Overhaul: Disassembly Procedure:




17. Push the shift lever sealing plate (1) into the housing.

Assembly Procedure:




18. Install the commutator end shield washers
19. Install the commutator end shield bolts (2) to the starter motor.
Tighten
Tighten the bolts to 5 N.m (44 lb in).

Assembly Procedure:




20. Install the solenoid.
21. Install the solenoid screws.
Tighten
Tighten the screws to 5 N.m (44 lb in).

22. Install the solenoid field lead.
23. Install the lead nut (2).
Tighten
Tighten the nut to 8 N.m (71 lb in).

24. Install the starter motor.