| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
Tune-Up | 1.4 | 0.0 | B | Includes: R&R Trans Pan, Service Filter And Make All Necessary Adjustments. |
Diagnose/Test |
4 Speed, A604, 41AE, 41TE |
Electronic Trans, Diagnosis | 1.8 | 0.0 | A | Includes: Time To Hook-Up And Disconnect Test Equipment. Checking System For Fault Codes, Road Test And Hydraulic Pressure Test As Required. |
Replace |
4 Speed, A604, 41AE, 41TE |
Complete Assembly Without Transfer of Parts | 3.9 | 2.8 | B | |
Note |
With A.B.S., Add | 0.4 | 0.2 | B | |
To Renew Driveplate, Add | 0.4 | 0.2 | B | |
To Check Cooler System Flow, Add | 0.7 | 0.4 | B | |
To Reverse Flush Cooler System, Add | 0.8 | 0.5 | B | |
To Replace Torque Converter, Add | 0.2 | 0.2 | B | |
Complete Assembly With Transfer of Parts | 4.6 | 3.0 | B | Includes: R&I Transaxle. |
Note |
With A.B.S., Add | 0.4 | 0.2 | B | |
To Renew Driveplate, Add | 0.4 | 0.2 | B | |
To Check Cooler System Flow, Add | 0.7 | 0.4 | B | |
To Reverse Flush Cooler System, Add | 0.8 | 0.5 | B | |
To Replace Torque Converter, Add | 0.2 | 0.2 | B | |
3 Speed, A670/31TH |
Complete Assembly Without Transfer of Parts | 3.8 | 2.7 | B | |
Note |
With A.B.S., Add | 0.4 | 0.2 | B | |
To Renew Driveplate, Add | 0.4 | 0.2 | B | |
To Check Cooler System Flow, Add | 0.7 | 0.4 | B | |
To Reverse Flush Cooler System, Add | 0.8 | 0.5 | B | |
To Replace Torque Converter, Add | 0.2 | 0.2 | B | |
Complete Assembly With Transfer of Parts | 4.4 | 3.1 | B | Includes: R&I Transaxle. |
Note |
With A.B.S., Add | 0.4 | 0.2 | B | |
To Renew Driveplate, Add | 0.4 | 0.2 | B | |
To Check Cooler System Flow, Add | 0.7 | 0.4 | B | |
To Reverse Flush Cooler System, Add | 0.8 | 0.5 | B | |
To Replace Torque Converter, Add | 0.2 | 0.2 | B | |
Overhaul/Rebuild |
4 Speed, A604, 41AE, 41TE | 10.5 | 7.6 | A | Includes: R&I Transaxle. |
Note |
With A.B.S., Add | 0.4 | 0.2 | A | |
To Renew Driveplate, Add | 0.4 | 0.2 | A | |
To Check Cooler System Flow, Add | 0.7 | 0.4 | A | |
To Reverse Flush Cooler System, Add | 0.8 | 0.5 | A | |
To Replace Torque Converter, Add | 0.4 | 0.2 | A | |
3 Speed, A670/31TH | 9.7 | 6.9 | A | Includes: R&I Transaxle. |
Note |
With A.B.S., Add | 0.4 | 0.2 | A | |
To Renew Driveplate, Add | 0.4 | 0.2 | A | |
To Check Cooler System Flow, Add | 0.7 | 0.4 | A | |
To Reverse Flush Cooler System, Add | 0.8 | 0.5 | A | |
To Replace Torque Converter, Add | 0.4 | 0.2 | A | |