Installation






INSTALLATION

3.7L / 4.7L

1. Connect solenoid wire to starter motor (snaps on).

2. Position battery cable to solenoid stud. Install and tighten battery cable eyelet nut to 19 ft. lbs. (25 Nm). Do not allow starter motor to hang from wire harness.

3. Position starter motor to transmission.

4. If equipped with automatic transmission, slide cooler tube bracket into position.

5. Install and tighten both bolts (auto. trans.), or 1 nut and 1 bolt (man. trans.) to 50 ft. lbs. (68 Nm).

6. Lower vehicle.

7. Connect negative battery cable.

5.7L

1. Connect solenoid wire to starter motor (snaps on).

2. Position battery cable to solenoid stud. Install and tighten battery cable eyelet nut. Refer to Torque Specifications. Do not allow starter motor to hang from wire harness.

3. Position starter motor to engine.

4. If equipped with automatic transmission, slide cooler tube bracket into position.

5. Install and tighten both mounting bolts to 30 ft. lbs. (41 Nm).. Refer to Torque Specifications.

6. Lower vehicle.

7. Connect negative battery cable.