Line Pressure Control Solenoid - PC-A
Torqshift Automatic TransmissionLine Pressure Control Solenoid - PC-A
Material:
Removal
1. With the vehicle in NEUTRAL, position it on a hoist. For additional information, refer to Maintenance/Service and Repair.
2. Remove the transmission main control valve body.
3. Remove the solenoid body electrical connector O-ring seal.
4. Partially remove the solenoid body electrical wire harness.
1 Remove the wire harness-to-solenoid body bolts.
2 Disconnect the electrical connector from the pressure control solenoid (PC-A) and the shift solenoid (SSPC-C)
3 Lift the tab on the bulkhead connector, twist and push the bulkhead connector through the solenoid body.
5. Remove the pressure control solenoid (PC-A).
1 Remove the (E) retaining clips from the pressure control solenoid (PC-A) and the shift solenoid (SSPC-C).
2 Partially slide the shift solenoid (SSPC-C) back enough to gain clearance to remove the pressure control solenoid (PC-A).
3 Remove the pressure control solenoid (PC-A).
Installation
1. Assemble the main control valve body.
1 Install the pressure control solenoid (PC-A) and install the (E) retaining clip.
2 Push the bulkhead connector through the solenoid body and twist the bulkhead connector locking it into place
3 Install the shift solenoid (SSPC-C) back into place and install the (E) retaining clip.
4 Connect the electrical connectors to the pressure control solenoid (PC-A) and the shift solenoid (SSPC-C).
5 Install the wire harness to solenoid body and tighten the bolts.
2. Remove the solenoid body electrical connector O-ring seal.
3. Install the transmission main control valve body.