Tests AG: DTC B1360 - Ignition Run/Acc Circuit Open
PINPOINT TEST AG: DTC B1360 - IGNITION RUN/ACC CIRCUIT OPENNormal Operation
With the ignition switch in the START or RUN position, the instrument cluster (IC) receives voltage from the central junction box (CJB) through circuit 1044 (WH/YE). When the ignition switch is in the RUN or ACC position, voltage is received from the CJB through circuit 295 (LB/PK). With the ignition switch in the OFF position, the instrument cluster (IC) receives its keep-alive voltage from the CJB through circuit 729 (RD/WH). The instrument cluster (IC) grounding is through circuits 938 (BK/LG) and 57 (BK). DTC B1360 is a continuous and on-demand DTC that sets in the instrument cluster (IC) if the instrument cluster (IC) detects voltage on circuit 1044 (WH/YE) for 15 seconds without voltage applied to circuit 295 (LB/PK).
This pinpoint test is intended to diagnose the following:
- Wiring, terminals or connectors
- Instrument cluster (IC)