Operation CHARM: Car repair manuals for everyone.

Pinpoint Test B: No Power In ACC




Steering Column Switches

Pinpoint Tests

Pinpoint Test B: No Power in ACC

Normal Operation

When placed in the ACC position, the ignition switch provides fused ignition voltage to the Smart Junction Box (SJB) along circuit CDC33 (VT/OG).

This pinpoint test is intended to diagnose the following:
- Wiring, terminals or connectors
- Fuse
- Ignition switch
- SJB


PINPOINT TEST B: NO POWER IN ACC

-------------------------------------------------
B1 CHECK THE IGNITION SWITCH


- Carry out the Ignition Switch - Electrical Component Test. Component Tests and General Diagnostics
- Does the ignition switch test OK?

Yes
GO to B2.

No
INSTALL a new ignition switch. REFER to Ignition Switch Ignition Switch. TEST the system for normal operation.

-------------------------------------------------
B2 CHECK THE ECU DERIVED IGNITION STATE-ACC (IGN_A_ECU) PID


- Connect the scan tool.
- Ignition ON.
- Enter the following diagnostic mode on the scan tool: DataLogger - SJB.
- Monitor the IGN_A_ECU PID while placing the ignition switch in the ACC position.
- Does the PID match the switch position?

Yes
The condition is not present at this time. INSPECT ignition switch C250 and SJB C2280A for corrosion, pushed-out pins and/or spread terminals. REPAIR as necessary. TEST the system for normal operation.

No
GO to B3.

-------------------------------------------------
B3 CHECK THE SJB ACC INPUT FOR AN OPEN


- Ignition OFF.
- Disconnect: Ignition Switch C250.
- Disconnect: SJB C2280A.
- Measure the resistance between ignition switch C250-3, circuit CDC33 (VT/GN), harness side and SJB C2280A-3, circuit CDC33 (VT/GN), harness side.




- Is the resistance less than 5 ohms?

Yes
GO to B4.

No
REPAIR circuit CDC33 (VT/GN). TEST the system for normal operation.

-------------------------------------------------
B4 CHECK THE SJB ACC INPUT FOR A SHORT TO GROUND


- Measure the resistance between ignition switch C250-3, circuit CDC33 (VT/GN), harness side and ground.




- Is the resistance greater than 10,000 ohms?

Yes
INSTALL a new SJB. REFER to Multifunction Electronic Modules Service and Repair. TEST the system for normal operation.

No
REPAIR circuit CDC33 (VT/GN). TEST the system for normal operation.

-------------------------------------------------