| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
Diagnose/Test |
Oil Leak, Diagnosis | 0.8 | 0.0 | B | Includes: Clean And Dry Outside Of Case And Operating Unit To Determine Point Of Leakage. |
Transmission, Diagnosis | 1.8 | 0.0 | A | Includes: Time To Hook-Up And Disconnect Test Equipment. Checking System For Fault Codes, Road Test And Hydraulic Pressure Test As Required. |
Replace |
Complete Assembly Without Transfer Of Parts |
4L60E, 4L65E, 4L70E | 8.2 | 0.0 | B | |
NOTE |
With Skid Plate, Add | 0.4 | 0.0 | B | |
To R&R Driveplate, Add | 0.2 | 0.0 | B | |
To R&R Torque Converter, Add | 0.2 | 0.0 | B | |
Complete Assembly With Transfer Of Parts |
4L60E, 4L65E, 4L70E | 8.8 | 5.5 | B | |
NOTE |
With Skid Plate, Add | 0.4 | 0.2 | B | |
To R&R Driveplate, Add | 0.2 | 0.2 | B | |
To R&R Torque Converter, Add | 0.2 | 0.0 | B | |
To Flush Cooler Lines, Add | 0.6 | 0.0 | B | |
Overhaul/Rebuild |
4L60E, 4L65E, 4L70E | 15.9 | 0.0 | A | |
NOTE |
With Skid Plate, Add | 0.4 | 0.2 | A | |
To Overhaul Valve Body, Add | 1.5 | 0.7 | A | |
To R&R Torque Converter, Add | 0.2 | 0.0 | A | |
To Flush Cooler Lines, Add | 0.6 | 0.0 | A | |