Daytime Running Lamp Control Unit: Testing and Inspection
DRL CONTROL MODULEINSPECTION
1. The daytime running unit (A) is integrated in the BCM.
2. Check that the light operate according to the following timing chart.
1. Operation condition
a. DRL ON
- ALT L signal and IGN2 signal input
b. DRL operation
- Lighting the head lamp high beam and tail SW OFF.
c. DRL OFF
- Brake SW ON.
- Head lamp SW ON or Head lamp high beam SW (or passing SW) ON.
- Until vehicle is not moving after ALT "L" signal ON.
3. If the daytime running light is not operated well, Inspect the connector and terminals to be sure they are all making good contact.
If the terminals are bent, loose or corroded, repair them as necessary, and recheck the system. If the terminals look OK, go to step 4.
4. Make these input tests at the connector by using ETM. If any test indicates a problem, find and correct the cause, then recheck the system.
If all the input tests prove OK, the BCM (Body control module) must be faulty; replace it.