Test Procedures:
NOTE: If the engine starts when testing to confirm a no start condition, refer back to the original customer complaint and then determine the appropriate action as per this test procedure.Test Procedures:
- Test 1 - JLM 9992 Battery Focus Book
Battery Test DBC 5994/5 Technical Bulletin
Section 86, number 66
- Test 2 - Technical Bulletin
Battery recharge prior Section 86, number 56
to test, new policy
- Test 3 - 88/89 Sedans Battery Focus Book Quiescent Drain Test
90 MY Sedans Technical Bulletin
Section 86, number 68
Warranty Information:
Model: Repair Operation: Time Allowance:
Sedan Range 86.15.01 Battery Renew .25 hrs.
86.15.02 Battery Test .10 hrs.
XJ-S 86.15.01 Battery Renew .15 hrs.
86.15.02 Battery Test .10 hrs.
Quiescent drain test is at shop rate for both models.