Operation CHARM: Car repair manuals for everyone.

Up to 08/2009





METER / GAUGE / DISPLAY: COMBINATION METER: INSTALLATION

1. INSTALL COMBINATION METER ASSEMBLY

(a) Connect each connector.

(b) Install the combination meter assembly with the 2 screws.





2. INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL

(a) Engage the 4 clips and 2 guides.





(b) Install the No. 1 instrument cluster finish panel with the 2 clips and 2 screws.

3. INSTALL NO. 2 INSTRUMENT PANEL HOLE COVER Installation

4. INSTALL NO. 1 INSTRUMENT PANEL HOLE COVER Installation

5. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY Installation

6. INSTALL NO. 1 SWITCH HOLE BASE Installation

7. INSTALL INSTRUMENT PANEL GARNISH LH Installation

8. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
* Make sure that the cable has been disconnected from the negative (-) battery terminal for at least 2 seconds before reconnecting the cable.
* Reset the auto tilt away function setting to the previous condition by changing the customize parameter Programming and Relearning.
* When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
9. INSPECT SUSPENSION CONTROL SYSTEM (w/ Air Suspension)

(a) Inspect the suspension control system Test Mode Procedure.