Up to 08/2009
2GR-FE ENGINE CONTROL: IGNITION COIL AND SPARK PLUG: INSTALLATION
1. INSTALL SPARK PLUG
(a) Install the 6 spark plugs.
Torque : 18 Nm (184 kgf-cm, 13 ft-lbf)
2. INSTALL IGNITION COIL ASSEMBLY
(a) Install the 6 ignition coils with the 6 bolts.
Torque : 10 Nm (102 kgf-cm, 7 ft-lbf)
(b) Connect the 6 ignition coil connectors.
(c) Connect the 3 wire harness clamps.
3. INSTALL NO. 1 SURGE TANK STAY Installation
4. INSTALL INTAKE AIR SURGE TANK ASSEMBLY Installation
5. INSTALL AIR CLEANER ASSEMBLY Installation
6. INSTALL BATTERY Installation
7. INSTALL NO. 1 AIR CLEANER INLET Installation
8. INSTALL NO. 2 AIR CLEANER INLET Installation
9. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
10. ADD ENGINE COOLANT Service and Repair
11. INSPECT FOR ENGINE COOLANT LEAK Testing and Inspection
12. INSTALL V-BANK COVER SUB-ASSEMBLY Installation
13. INSTALL OUTER COWL TOP PANEL SUB-ASSEMBLY Installation
14. INSTALL FRONT SHOCK ABSORBER CAP (w/ Air Suspension) Installation
15. INSTALL WINDSHIELD WIPER MOTOR AND LINK ASSEMBLY
(a) Install the windshield wiper motor and link assembly Installation.
16. INSTALL NO. 1 ENGINE UNDER COVER