V. Work Procedure
1. PRELIMINARY INSPECTIONa) Check for DTCs. If DTCs are present confirm the code(s) view and record the freeze frame data and perform repairs as necessary.
2. CONFIRM THAT THE IGNITION IS OFF
3. REMOVE THE LEFT SIDE ENGINE ROOM COVER
a) Remove the 4 clips and the left side engine room cover.
4. REMOVE THE NO.1 RELAY BLOCK COVER
a) Release the lock and disengage the 2 claws to remove the No. 1 relay block cover.
NOTE:
Take measures to prevent water, etc. from entering the relay block when removing the cover.
5. INSTALL THE AIR CONDITIONING WIRE HARNESS SUB-ASSEMBLY
a) Disconnect the 22 pin connector as illustrated.
b) Connect the air conditioning wire harness sub-assembly into the location where the 22 pin connector was removed.
c) Reconnect the 22 pin connector to the air conditioning wire harness sub-assembly as illustrated.
NOTE:
After the installation, do not bend the sub-wire harness excessively.
6. REINSTALL THE NO.1 RELAY BLOCK COVER
a) Engage the 2 claws and the lock to reinstall the No.1 relay block cover.
7. REINSTALL THE LEFT SIDE ENGINE ROOM COVER
a) Insert the left side engine room cover into the guide.
b) Reinstall the 4 clips.
8. FINAL INSPECTION
a) Start the vehicle and increase the engine speed to approximately 2,000 RPM and verify the engine operates smoothly.
b) Confirm that no warning lamps in the combination meter are illuminated.
c) Check for DTCs. If DTCs are present confirm the code(s) view and record the freeze frame data and perform repairs as necessary.
d) Confirm normal air conditioner compressor operation.