From 08/2009
METER / GAUGE / DISPLAY: HEAD-UP DISPLAY: INSTALLATION
1. INSTALL COMBINATION METER MIRROR ECU
(a) Install the combination meter mirror ECU with the 4 screws.
NOTICE:
* Make sure that the ECU is installed securely.
* Do not drop the screws.
(b) Engage the clamp.
(c) Connect the connector.
(d) Insert the No. 1 heater to register duct in the order indicated in the illustration to temporarily install it.
(e) Install the No. 1 heater to register duct with the 2 screws.
(f) Connect the connectors.
2. INSTALL COMBINATION METER ASSEMBLY Installation
3. INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL Installation
4. INSTALL NO. 2 INSTRUMENT PANEL HOLE COVER Installation
5. INSTALL NO. 1 INSTRUMENT PANEL HOLE COVER Installation
6. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY Installation
7. INSTALL NO. 1 SWITCH HOLE BASE Installation
8. INSTALL INSTRUMENT PANEL GARNISH LH Installation
9. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
* Make sure that the cable has been disconnected from the negative (-) battery terminal for at least 2 seconds before reconnecting the cable.
* Reset the auto tilt away function setting to the previous condition by changing the customize parameter Programming and Relearning.
* When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
10. INSTALL REAR DECK FLOOR BOX Installation
11. INSPECT SUSPENSION CONTROL SYSTEM (w/ Air Suspension)
(a) Inspect the suspension control system Test Mode Procedure.