Operation CHARM: Car repair manuals for everyone.

Fuel Door Release Cable: Testing and Inspection

FUEL LID LOCK CONTROL CABLE ASSEMBLY

INSPECTION

1. INSPECT LUGGAGE DOOR OPENING SWITCH ASSEMBLY (FUEL LID OPENING SWITCH)









a. Measure the resistance of the switch.

If the result is not as specified, replace the switch assembly.

2. INSPECT FUEL LID LOCK CONTROL CABLE SUB-ASSEMBLY (FUEL LID OPENER MOTOR)









a. Check the operation of the motor.
1. Apply battery voltage to the motor and check the operation of the motor.

If the result is not as specified, replace the cable sub-assembly.

b. Measure the shaft strokes.

Standard stroke: 10.3 mm (0.406 in.) or more

If the result is not as specified, replace the cable sub-assembly.