METER: COMBINATION METER:

INSTALLATION

1. INSTALL COMBINATION METER ASSEMBLY





(a) Connect the 2 connectors as shown in the illustration.





(b) Install the combination meter assembly as shown in the illustration.





(c) Install the 4 screws.
2. INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY





(a) Engage the guide and 4 claws.
(b) Engage the 2 clips.
(c) Install the instrument cluster finish panel sub-assembly with the screw.
3. INSTALL STEERING COLUMN COVER





(a) Engage the claw and install the upper steering column cover.





(b) Engage the 2 claws.
(c) Install the lower steering column cover with the 2 screws.
Torque: 2.0 Nm (20 kgf-cm, 18 in-lbf)
4. INSTALL LOWER INSTRUMENT PANEL SUB-ASSEMBLY Installation
5. INSTALL INSTRUMENT PANEL FINISH PANEL END LH Installation
6. INSTALL SIDE INSTRUMENT PANEL LH Installation
7. INSTALL FRONT DOOR OPENING TRIM COVER LH Installation
8. INSTALL FRONT DOOR SCUFF PLATE LH Installation
9. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
10. PERFORM INITIALIZATION
NOTE:
Some systems need initialization after reconnecting the cable to the negative battery terminal Repair Instruction - Initialization.