INTRODUCTION: REPAIR INSTRUCTION: INITIALIZATION
INITIALIZATION (Continued)
22. REGISTRATION (FOR LEXUS LINK SYSTEM)
HINT:
- Turn the power switch OFF and disconnect the vehicle battery before replacing the mayday ECU (together with mayday battery) or when just replacing the mayday battery.
- Historic DTCs may be set if the vehicle battery is not disconnected during ECU installation/replacement.
- The mayday ECU estimates the remaining power of the mayday battery based on the mayday battery usage time.
(a) LEXUS Link Operation Modes
(1) Factory Mode
This is the default mode from the factory. In this mode, a Japanese prompt will play when the power switch is turned ON (IG). After any button is pressed, a voice prompt will play "System not initialized, a call cannot be placed."
(2) Demo Mode (Dealer Mode)
A button sequence will initialize the mayday ECU from Factory Mode into Demo Mode. In Demo Mode, pressing the SERVICES button will play the voice prompt "Hello and welcome to LEXUS Link. For LEXUS Link services, contact a LEXUS Link advisor by pressing the SERVICES button again. For additional information, visit us Online at Lexus.com in the owner section or talk to your LEXUS dealer." Pressing the SERVICES button again during this voice prompt will place an enrollment call to the LEXUS Link call center.
HINT:
- See "MAYDAY ECU INITIALIZATION" for the button sequence to switch the ECU from Factory Mode into Demo Mode.
- If the ECU will not switch from Factory Mode to Demo Mode, and there are no prompts played when pushing any buttons, the ECU may have been inadvertently placed into an Engineering Mode. In this case, perform this button sequence to switch the ECU back into Factory Mode. While pressing and holding the VOL- button, press the SERVICES button 5 times within 15 seconds, then release both buttons. The ECU will perform a Factory Mode Start Sequence as described under "MAYDAY ECU INITIALIZATION".
(3) Active Mode
The LEXUS Link call center will configure this mode automatically after customer enrollment.
(4) De-active Mode
The LEXUS Link call center will configure this mode automatically after an enrollment expires. The SERVICES button will operate the same as in Demo Mode. Therefore, the customer can push it twice to contact the LEXUS Link call center for re-enrollment.
(b) MAYDAY ECU INITIALIZATION
HINT: This procedure is for switching a new mayday ECU from the Factory Mode into Demo Mode.
(1) Turn the power switch from OFF to ON (IG) (engine does not have to be running).
(2) The mayday ECU will perform the Factory Mode Start Sequence for approximately 30 seconds.
HINT:
- In Factory Mode, for each power switch cycle OFF to ON (IG), or after checking or clearing DTCs, the ECU will perform a start sequence that includes a Japanese prompt and flashing LEDs (approximately 30 seconds). Then the LEDs will turn off. Do not push any buttons during this start sequence.
- If there is a DTC detected during this Factory Mode Start Sequence, after the start sequence, the red LED will remain on and a Japanese prompt will repeat 5 times. Do not press any buttons during these prompts.
(3) BUTTON SEQUENCE:
While pressing and holding the VOL+ button, press and release the PHONE button 5 times within 15 seconds, then release the VOL+ button. When switched to Demo Mode, each LED will flash one time then turn off (approximately 5 seconds).
(4) CONFIRMATION:
Confirm Demo Mode by pressing the SERVICES button and listening for the demo prompt "Hello and welcome to LEXUS Link." (the power switch must be ON (IG) for the SERVICES button to function). Additionally, after each power switch cycle OFF to ON (IG), the LEDs will each flash one time each. This start sequence takes approximately 5 seconds. If Demo Mode is not confirmed, repeat the initialization procedure.
HINT:
- Before troubleshooting a DTC, attempt to initialize the ECU into Demo Mode with the button sequence. Then access DTCs and troubleshoot the ECU in Demo Mode. If necessary, DTCs can still be accessed in Factory Mode. However, the 30 second Factory Mode Start Sequence (and the Japanese prompt will repeat 5 times if a DTC is set) will occur after each power switch cycle OFF to ON (IG), and after each DTC check or clear. Do not press any buttons during this start sequence.
- A red LED continuously on in any mode indicates that there is a current DTC set. Refer to the DTC chart.
- Do not push any buttons during any start sequences (LED flashing or voice prompts).
(c) MAYDAY ECU REGISTRATION / ENROLLMENT
(1) Turn the power switch ON (IG) and wait for the 5 second LED flash start sequence. Press the SERVICES button when the mayday ECU is set normally and confirm that the following demo message is provided.
"Hello and welcome to LEXUS Link."
If the message is not provided, perform the "MAYDAY ECU INITIALIZATION BUTTON SEQUENCE" again.
(2) As the message states, press the SERVICES button again during the prompt to connect to the LEXUS Link call center.
HINT: Usually this call will connect within 15 to 30 seconds. However, it may take several minutes depending on cellular service in the area. A progression tone (i.e., beep) will be heard every 5 seconds to indicate that the connection attempt is in progress.
(3) A LEXUS Link call center advisor will answer and instruct the technician on how to register/enroll the new mayday ECU. The ESN, STID and VIN may be required at this time.
HINT:
- If the LEXUS Link call center cannot be reached after several attempts using the SERVICES button, or a cell tower message is heard, such as "Welcome to Verizon Wireless, your phone is not active at this time.", call the LEXUS Link call center by pushing the EMERGENCY button.
- The LED flash start sequence (approximately 5 seconds) after power switch is cycled or after checking/clearing DTCs remains present after enrollment. A green LED continuously on after this sequence indicates that the LEXUS Link System is activity enrolled.
(d) MAYDAY BATTERY REGISTRATION
HINT:
- This procedure is required to register a new mayday battery and clear DTC 6-1. This procedure matches the new mayday battery with the new or used ECU.
- A new mayday ECU always requires a new mayday battery (used mayday batteries should not be reused in a new ECU).
- If the new replacement ECU is packaged and already connected to the new mayday battery when it arrives from the factory, and current DTC 6-1 is not set, do not perform the new mayday battery registration (the battery is already registered to the ECU that it is connected to).
(1) Turn the power switch from OFF to ON (IG) and wait for the start up sequence of LED flashing to complete. Do not press any buttons during this start up sequence.
(Note that Demo Mode and active enrolled ECUs have approximately a 5 second LED flashing start sequence. Factory Mode has approximately 30 seconds of LED flashing with a Japanese voice prompt. Also note if a current DTC is set in Factory Mode after this start sequence. This can be confirmed if the red LED remains on and an additional Japanese prompt repeats 5 times.)
(2) BUTTON SEQUENCE:
Press and hold the PTT button while completing the following sequence of button presses.
VOL+, VOL+, VOL-, VOL-, VOL+, VOL+, VOL-, VOL-, VOL+, VOL+, VOL-, VOL-
Release all buttons. This button press sequence should be performed within 15 seconds.
(3) The system will then perform the same start sequence as described above. After this start sequence completes, cycle the power switch to OFF then ON (IG). Wait for the start sequence to complete. The new mayday battery is now registered to the mayday ECU and DTC 6-1 should be cleared.
HINT: The mayday battery registration can be done in any mode (Factory Mode, Demo Mode or activity enrolled).
(e) MAYDAY BATTERY CONFIRMATION
(1) After replacement check: If the "MAYDAY BATTERY REGISTRATION BUTTON SEQUENCE" has been completed, turn the power switch OFF and ON (IG), and wait for the start sequence described in the "MAYDAY BATTERY REGISTRATION". Then check that current DTC 6-1 is cleared.
NOTICE:
If the "MAYDAY BATTERY REGISTRATION BUTTON SEQUENCE" has not been completed correctly, current DTC 6-1 will continue to be detected even if the mayday battery is replaced with a new one. In this case, check to be sure the old battery is removed and the new battery is installed. Then perform the "MAYDAY BATTERY REGISTRATION BUTTON SEQUENCE" again.
23. PERFORM INITIAL SETTING OF STEERING ANGLE MID-POINT AND MAXIMUM STEERING ANGLE
HINT: The mid-point learning operation (steering angle mid-point, maximum steering angle) can be performed using 4 methods:
(a) Method 1 (Techstream)
(1) Turn the power switch off.
(2) Connect the Techstream to the DLC3.
(3) Turn the power switch ON (IG).
(4) Turn the Techstream on.
(5) Enter the following menus: Body Electrical / INTUITIVE P/A / Utility.
(6) Perform the STEERING INITIALIZATION procedure.
(b) Method 2 (Manual operation method)
(1) Using customize mode, set the mid-point and maximum steering angle.
HINT:
- *1: Steering wheel is centered (tires aligned straightforward).
- *2: If 180 seconds pass, steering angle mid-point setting and maximum steering angle range setting will not occur and initialize mode will end.
Multi-information Display Indication Settings in Each Mode
- y : Illumination
- o : Flashing
- a: Flashes depending on condition
- x : No illumination or flashing
(c) Method 3 (Manual operation method)
(1) Turn the power switch on (IG).
(2) Turn the clearance sonar main switch ON.
(3) Turn the steering wheel to the full left and right lock position.
NOTICE:
Make sure to completely turn the steering wheel to the left and right full lock position.
(d) Method 4 (Manual operation method)
(1) At an area with few turns and curves, and minimal traffic, drive at 20 km/h (12 mph) or more for 5 minutes or more.
24. INITIALIZE POWER WINDOW CONTROL SYSTEM (POWER WINDOW REGULATOR MOTOR (ALL DOORS))
CAUTION:
When the power window regulator motor is reinstalled or replaced, the power window control system must be initialized. Functions such as the auto up/down, jam protection and key-off do not operate if the initialization is not performed.
HINT: When the battery is replaced, it is not necessary to initialize the power window regulator motor.
NOTICE:
- When the power window regulator motor is replaced, DTC B2313 is output. Clear the DTC after the initialization.
- When performing initialization, do not perform any other procedures.
- After a door glass or a door glass run has been replaced, the jam protection function may operate unexpectedly when the auto up function is used, due to detection of a value different from the operation learned value of the door glass movement speed. In such cases, the auto up function can be resumed by repeating the following operation at least 5 times:
1 Open the power window by fully pushing down the power window switch.
2 Close the power window by fully pulling up the power window switch and holding it at the auto up position.
- If the initialization is not completed properly, the LIN communication line may have a malfunction.
- If the initialization is not completed properly, the BEAN communication system may have a malfunction How to Proceed With Troubleshooting.
(a) Initialization procedures when replacing the power window regulator motor with a new one:
(1) Connect the battery and turn the power switch on (IG) (at this time, the LED on the power window switch blinks to indicate that it is ready for initialization).
(2) Fully open the window by fully pushing the power window switch, and hold the switch for 1 second or more after the window is fully opened.
(3) Fully close the power window by fully pulling the power window switch, and hold the switch for 1 second or more after the window is fully closed to reset the glass position. The LED on the power window switch stops blinking and illuminates to indicate that initialization is complete.
(b) Initialization procedures when removing/installing the power window regulator motor:
(1) Connect the battery and turn the power switch on (IG).
(2) Fully close the power window by fully pulling the power window switch, and hold the switch for 6 seconds or more after the window is fully closed (if the power window does not move or stops halfway even when the switch is fully pulled, release the switch and fully pull it again).
(3) Fully open the window by pushing down the power window switch, and hold the switch for 1 second or more after the window is fully opened.
(4) Release the power window switch. Then fully push and hold the switch for 4 seconds or more.
(5) Fully close the power window by fully pulling the power window switch, and hold the switch for 1 second or more after the window is fully closed to reset the glass position and complete initialization.
(c) Initialization procedures when the power window does not fully open:
(1) Connect the battery and turn the power switch on (IG).
(2) Fully close the power window by fully pulling the power window switch, and hold the switch for 6 seconds or more after the window is fully closed (if the power window does not move or stops halfway even when the switch is fully pulled, release the switch and fully pull it again).
(3) Fully open the window by pushing down the power window switch, and hold the switch for 1 second or more after the window is fully opened.
(4) Release the power window switch. Then fully push and hold the switch for 4 seconds or more.
(5) Fully close the power window by fully pulling the power window switch, and hold the switch for 1 second or more after the window is fully closed to reset the glass position and complete initialization.
25. RESET SLIDING ROOF SYSTEM
NOTICE:
When replacing the sliding roof drive gear or sliding roof related parts, the sliding roof drive gear requires initialization. If a reset is not executed, the following functions do not operate: auto operation, jam protection function, key off operation, key-linked open and close, and transmitter-linked open and close.
(a) Turn the power switch ON (IG).
(b) If the sliding roof is opened, close it fully.
(c) Push the SLIDE CLOSE switch or TILT UP switch, making the sliding roof operation as follows:
Tilt up -> Approximately 1 second -> tilt down -> slide open -> slide close
(d) Sliding roof stops at the fully closed position.
(e) Finish the initialization.
(f) Check that the operation works normally with AUTO operation.
NOTICE:
If the following conditions occur while operating, initialization will fail.
- Power switch is turned OFF.
- Pushed switch is released while sliding roof is operating.
- Vehicle speed is 5 km/h (3 mph) or higher.
- Battery of sliding roof ECU is 1 V or higher.
- Communication is cut off.
HINT:
- If the sliding roof cannot fully close or its position has become misaligned, perform the initialization again.
- If the sliding roof TILT UP switch or SLIDE CLOSE switch is pressed and held until the roof glass has either stopped moving or started moving in the opposite direction, and then the switch is held for another 10 seconds or more, perform the initialization again.