Installation
METER / GAUGE / DISPLAY: LIGHT CONTROL RHEOSTAT: INSTALLATION
1. INSTALL LIGHT CONTROL RHEOSTAT
(a) Engage the 2 claws and install the light control rheostat.
(b) Install the finish panel No. 2 retainer with switch with the 3 screws.
2. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY Installation
3. INSTALL SIDE INSTRUMENT PANEL LH Installation
4. INSTALL FRONT DOOR OPENING TRIM COVER LH Installation
5. INSTALL FRONT DOOR SCUFF PLATE LH Installation