Installation
U660E AUTOMATIC TRANSAXLE: AUTOMATIC TRANSAXLE ASSEMBLY: INSTALLATION
1. INSPECT TORQUE CONVERTER CLUTCH ASSEMBLY
HINT
Testing and Inspection
2. INSTALL TORQUE CONVERTER CLUTCH ASSEMBLY
(a) Engage the splines of the input shaft and turbine runner.
(b) Engage the splines of the stator shaft and the stator while turning the torque converter clutch assembly.
HINT
If the stator shaft splines are difficult to engage with the stator splines, move the torque converter back approximately 10 mm (0.393 in.) and engage the splines while rotating the torque converter.
(c) Turn the torque converter clutch assembly to engage the key of the oil pump drive gear into the slot on the torque converter clutch assembly.
(d) Using a vernier caliper and a straightedge, measure dimension "A" between the transaxle fitting surface of the engine *1 and the torque converter fitting surface of the drive plate *2. (#)
NOTICE:
Make sure to deduct the thickness of the straightedge.
(e) Using a vernier caliper and a straightedge, measure dimension "B" shown in the illustration and check that dimension "B" is greater than dimension "A" ,which was measured in step (#).
Standard:
A + 1 mm (0.04 in.) or more
HINT
In the case of where a U660E is used with a 2GR-FE, the standard installation depth is 14 mm (0.55 in.) or more.
NOTICE:
* Make sure to deduct the thickness of the straightedge.
* If the transaxle is installed to the engine with the torque converter not sufficiently inserted, the torque converter may be damaged.
3. INSTALL NO. 1 OIL COOLER INLET HOSE
(a) Install the No. 1 oil cooler inlet hose.
4. INSTALL NO. 1 OIL COOLER OUTLET HOSE
(a) Install the No. 1 oil cooler outlet hose.
5. INSTALL NO. 1 TRANSMISSION CONTROL CABLE BRACKET
(a) Install the No. 1 transmission control cable bracket with the 2 bolts.
Torque : 12 Nm (122 kgf-cm, 9 ft-lbf)
6. INSTALL WIRE HARNESS CLAMP BRACKET
(a) Install the 4 clamp brackets and 4 bolts.
Torque : 8.4 Nm (86 kgf-cm, 74 in-lbf)
7. INSTALL SPEEDOMETER DRIVEN HOLE COVER SUB-ASSEMBLY
(a) Coat a new O-ring with ATF, and install it to the hole cover.
(b) Install the hole cover to the transaxle case with the bolt.
Torque : 5.5 Nm (56 kgf-cm, 49 in-lbf)
8. INSTALL TCM
(a) Install the TCM to the transaxle.
(b) Install and tighten the 2 bolts in the order shown in the illustration.
Torque : 11 Nm (115 kgf-cm, 8 ft-lbf)
9. INSTALL ENGINE MOUNTING FRONT BRACKET
(a) Install the engine mounting front bracket to the automatic transaxle with the 3 bolts.
Torque : 64 Nm (653 kgf-cm, 47 ft-lbf)
10. INSTALL AUTOMATIC TRANSAXLE ASSEMBLY
(a) Confirm that 2 knock pins are on the transaxle contact surface of the engine cylinder block before the transaxle installation.
(b) Apply clutch spline grease to the round of the crankshaft contact surface with the torque converter centerpiece.
Clutch spline grease:
Toyota Genuine Clutch Spline Grease or equivalent
Maximum spread:
About 1 g (0.0353 oz.)
(c) Install the automatic transaxle to the engine with the 11 bolts.
Bolt A - Torque : 64 Nm (653 kgf-cm, 47 ft-lbf)
Bolt B - Torque : 64 Nm (653 kgf-cm, 47 ft-lbf)
Bolt C - Torque : 46 Nm (469 kgf-cm, 34 ft-lbf)
Bolt D - Torque : 43 Nm (439 kgf-cm, 32 ft-lbf)
(d) Install the breather bracket to the camshaft housing sub-assembly LH with the bolt.
Torque : 5.5 Nm (56 kgf-cm, 49 in-lbf)
(e) Install the breather hose to the breather bracket.
11. INSTALL STARTER ASSEMBLY Installation
12. CONNECT CONNECTOR
(a) Connect the park/neutral position switch connector.
13. INSTALL WIRE HARNESS
(a) Connect the wire harness with the bolt.
Torque : 12 Nm (122 kgf-cm, 9 ft-lbf)
14. INSTALL ENGINE WIRE
15. INSTALL FRONT DRIVE SHAFT ASSEMBLY LH Installation
16. INSTALL FRONT DRIVE SHAFT ASSEMBLY RH Installation
17. INSTALL FRONT FRAME ASSEMBLY Installation
18. INSTALL VANE PUMP ASSEMBLY Installation
19. INSTALL ENGINE ASSEMBLY WITH TRANSAXLE Installation
20. INSTALL COOLER COMPRESSOR ASSEMBLY Installation
21. INSTALL GENERATOR ASSEMBLY Installation
22. INSTALL STEERING INTERMEDIATE SHAFT ASSEMBLY Installation
23. INSTALL DRIVE PLATE AND TORQUE CONVERTER CLUTCH SETTING BOLT
(a) Apply a few drops of adhesive to 2 threads of the 6 torque converter clutch mounting bolts tip.
Adhesive:
Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent
(b) Install the 6 torque converter clutch setting bolts while holding the crankshaft pulley bolt with a wrench.
Torque : 41 Nm (418 kgf-cm, 30 ft-lbf)
NOTICE:
Install the black colored bolt first, and then the silver colored 5 bolts.
(c) Install the flywheel housing under cover to the automatic transaxle with the 2 bolts.
Torque : 7.8 Nm (80 kgf-cm, 69 in-lbf)
24. INSTALL NO. 1 EXHAUST PIPE SUPPORT BRACKET Installation
25. INSTALL FRONT AXLE ASSEMBLY LH Installation
26. INSTALL FRONT AXLE ASSEMBLY RH
HINT
Use the same procedure described for the LH side.
27. INSTALL FRONT SUSPENSION LOWER NO. 1 ARM LH Installation
28. INSTALL FRONT SUSPENSION LOWER NO. 1 ARM RH
HINT
Use the same procedure described for the LH side.
29. INSTALL TIE ROD ASSEMBLY LH Installation
30. INSTALL TIE ROD ASSEMBLY RH
HINT
Use the same procedure described for the LH side.
31. INSTALL FRONT SPEED SENSOR LH Installation
32. INSTALL FRONT SPEED SENSOR RH
HINT
Use the same procedure described for the LH side.
33. INSTALL FRONT STABILIZER LINK ASSEMBLY LH Installation
34. INSTALL FRONT STABILIZER LINK ASSEMBLY RH
HINT
Use the same procedure described for the LH side.
35. INSTALL FRONT AXLE HUB NUT LH Installation
36. INSTALL FRONT AXLE HUB NUT RH
HINT
Use the same procedure described for the LH side.
37. INSTALL EXHAUST PIPE ASSEMBLY FRONT Installation
38. INSTALL EXHAUST PIPE NO. 1 SUPPORT BRACKET Installation
39. CONNECT OIL RESERVOIR TO PUMP HOSE Installation
40. CONNECT RETURN TUBE SUB-ASSEMBLY Installation
41. CONNECT FUEL TUBE SUB-ASSEMBLY Installation
42. CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY Installation
43. CONNECT ENGINE WIRE Installation
44. INSTALL RELAY BLOCK COVER UPPER
45. INSTALL ECM
Installation
46. CONNECT HEATER WATER HOSE INLET Installation
47. CONNECT HEATER WATER HOSE OUTLET Installation
48. CONNECT NO. 1 OIL COOLER INLET HOSE Installation
49. CONNECT NO. 1 OIL COOLER OUTLET HOSE Installation
50. INSTALL RADIATOR HOSE INLET Installation
51. INSTALL RADIATOR HOSE OUTLET Installation
52. CONNECT CHECK VALVE TO BRAKE BOOSTER HOSE Installation
53. CONNECT NO. 1 FUEL VAPOR FEED HOSE Installation
54. INSTALL ENGINE MOVING CONTROL ROD SUB-ASSEMBLY Installation
55. INSTALL NO. 2 ENGINE MOUNTING STAY RH Installation
56. INSTALL INTAKE AIR RESONATOR SUB-ASSEMBLY Installation
57. INSTALL BATTERY Installation
58. INSTALL NO. 1 AIR CLEANER INLET Installation
59. INSTALL AIR CLEANER CASE SUB-ASSEMBLY Installation
60. INSTALL AIR CLEANER CAP SUB-ASSEMBLY Installation
61. INSTALL AIR CLEANER INLET ASSEMBLY Installation
62. CONNECT VACUUM HOSES Installation
63. INSTALL V-RIBBED BELT Installation
64. INSTALL FRONT WHEELS Installation
65. ADD ENGINE OIL
66. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL Installation
67. ADD ENGINE COOLANT Testing and Inspection
68. ADD AUTOMATIC TRANSAXLE FLUID
HINT
Procedures
69. ADD POWER STEERING FLUID
70. BLEED POWER STEERING FLUID Service and Repair
71. CHECK FOR FUEL LEAKS Fuel System
72. CHECK FOR ENGINE OIL LEAKS
73. CHECK FOR ENGINE COOLANT LEAKS Testing and Inspection
74. CHECK FOR EXHAUST GAS LEAKS
75. CHECK SHIFT LEVER POSITION Initial Inspection and Diagnostic Overview
76. CHECK AND ADJUST FRONT WHEEL ALIGNMENT
HINT
Front Wheel Alignment
77. CHECK IGNITION TIMING On-Vehicle Inspection
78. CHECK ENGINE IDLE SPEED On-Vehicle Inspection
79. CHECK CO/HC On-Vehicle Inspection
80. CHECK FUNCTION OF THROTTLE BODY On-Vehicle Inspection
81. INSTALL FRONT FENDER APRON SEAL RH
82. INSTALL ENGINE UNDER COVER LH
83. INSTALL ENGINE UNDER COVER RH
84. INSTALL V-BANK COVER SUB-ASSEMBLY Installation
85. INSTALL ENGINE ROOM SIDE COVER LH Installation
86. INSTALL ENGINE ROOM SIDE COVER RH Installation
87. INSTALL COOL AIR INTAKE DUCT SEAL Installation
88. CHECK ABS SPEED SENSOR SIGNAL
HINT
Test Mode Procedure
89. PERFORM TCM REGISTRATION
HINT
Registration
90. PERFORM INITIALIZATION
(a) Perform initialization procedure Repair Instruction - Initialization.
NOTICE:
Some systems need initialization after reconnecting the cable to the negative battery terminal.