Installation
POWER DISTRIBUTION: POWER SOURCE CONTROL ECU: INSTALLATION
1. INSTALL POWER SOURCE CONTROL ECU
(a) Connect the connector.
(b) Install the power source control ECU with the bolt and 2 nuts.
Bolt - Torque : 11 Nm (107 kgf-cm, 8 ft-lbf)
Nut - Torque : 13 Nm (126 kgf-cm, 9 ft-lbf)
2. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY Installation
3. INSTALL FRONT PASSENGER SIDE KNEE AIRBAG ASSEMBLY Installation
4. INSTALL NO. 2 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY Installation
5. INSTALL INSTRUMENT SIDE PANEL RH Installation
6. INSTALL FRONT DOOR OPENING TRIM COVER RH
HINT
Use the same procedure for the RH side and LH side Installation.
7. INSTALL DOOR SCUFF PLATE ASSEMBLY RH
HINT
Use the same procedure for the RH side and LH side Installation.
8. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.