Installation
1. On level ground, jack up the vehicle and support it evenly on safety stands.
2. Install in the order shown in the image, referring to Installation Note.
3. Add the specified amount of the specified transmission oil.
4. Warm up the engine and transmission, and inspect for oil leakage and transmission problems.
Installation note
Transmission
1. Tilt the engine by pushing up on the front of the oil pan with a wooden block and a transmission jack.
2. Support the transmission with a transmission jack.
3. Raise the transmission into place and install and tighten the installation bolts.
Tightening torque: 64 - 89 N-m (6.5 - 9.1 kgf-m, 48 - 65 ft-lbf)
Power plant frame (PPF)
1. Install the differential mounting spacer.
Tightening torque: 38 - 51 N-m (3.8 - 5.3 kgf-m, 28 - 38 ft-lbf)
2. Support the transmission with a jack so that it is level.
3. Position the PPF and install the sleeve.
4. Install the spacer and bolts and snugly tighten the reamer bolt. The reamer bolt should be installed in the forward hole.
5. Tighten the outer bolts snugly.
6. Tighten the bolts to the specified torque in the order shown.
Tightening torque: 104 - 123 N-m (10.6 - 12.6 kgf-m, 77 - 91 ft-lbf)
7. Install the power plant frame bracket.
Tightening torque
(A): 104 - 123 N-m (10.6 - 12.6 kgf-m, 76.7 - 91.1 ft-lbf)
(B): 37 - 53 N-m (3.7 - 5.5 kgf-m, 27 - 39 ft-lbf)
8. Remove the jack, and connect the wire harness.
9. Measure distance (A) with a straightedge and vernier calipers.
Distance (A): 66.0 ± 5 mm (2.60 ± 0.197 in)
10. It the distance is not within the specification, reposition the PPF to the transmission.
Shift lever
1. Pour the specified amount of oil into the change control case. The change control case must also be tilled with the specified amount of oil whenever the extension housing has been removed or the transmission has been overhauled.
Specified oil
Grade: API service GL-4 or GL-5
All season: SAE 75W - 90
Above 10 °C (50 °F): SAE 80W - 90
Specified amount: 80 - 95 cc (4.9 - 5.8 cu in)
2. Apply oil to the shift lever as shown.
3. Apply sealant to the contact surfaces of the boot panel and the change control case.