Solenoid Valve Removal/Installation (Primary Control Valve Body)
SOLENOID VALVE REMOVAL/INSTALLATION (PRIMARY CONTROL VALVE BODY) [FS5A-EL]1. Remove the battery duct and battery cover.
2. Disconnect the negative battery cable.
3. Remove the under cover.
4. Drain the ATF,
5. Remove the oil pan.
6. Remove the primary control valve body.
7. Remove the solenoid valve(s).
8. Apply ATF to a new O-ring and install it on the solenoid valve.
9. Install the solenoid valve in the primary control valve body.
Tightening torque 7.8-10.8 N-m (80-110 kgf-cm, 70-95.4 in-lbf)
10. Install the primary control valve body.
11. Install the oil pan.
12. Install the under cover.
13. Connect the negative battery cable.
14. Install the battery duct and battery cover.
15. Add ATF.
16. Perform the mechanical system test. (See MECHANICAL SYSTEM TEST [FS5A-EL].) Mechanical System Test
17. Perform the road test. (See ROAD TEST [FS5A-EL].) Road Test