Operation CHARM: Car repair manuals for everyone.

Spool Valve Operation Inspection

Spool valve operation inspection
1. Verify that the spool valve in the OCV is in the maximum valve timing retard position as indicated in the figure.
^ If it exceeds the specification, replace the OCV.





2. Verify that the battery is fully charged. If it is less than specification, recharge the battery.
3. Apply battery positive voltage between the OCV terminals and verify that the spool valve operates and moves to the maximum valve timing advance position.
^ If it exceeds the specification, replace the OCV.

Note
^ When applying battery positive voltage between the OCV terminals, the connection can be either of the following:
^ Positive battery cable to terminal A, negative battery cable to terminal B
^ Positive battery cable to terminal B, negative battery cable to terminal A





4. Stop applying battery positive voltage and verify that the spool valve returns to the maximum valve timing retard position.
^ If it exceed the specification, replace the OCV.