Test F
Pinpoint Test F: DTC B1360 - Ignition ACC/RUN Circuit OpenNormal Operation
The ignition switch ACC/RUN circuit sends 12 volts through 687 (GY/YE) (on the CJB input side fuse 15 [5A]) and circuit 295 (LB/PK) (on the CJB output side fuse 15 [5A]) to the instrument cluster. The ignition switch RUN/START circuit sends 12 volts through 16 (RD./LG) (on the CJB input side fuse 30 [5A]) and circuit 489 (PK/BK) (on the CJB output side fuse 30 [5A]) to the instrument cluster. The instrument cluster monitors the output voltage from the ignition circuit and if an open circuit is detected, DTC B1360 will be set.
Possible Causes
^ CJB fuses:
- 15 (5A).
- 30 (5A).
^ circuit 295 (LB/PK)
^ circuit 489 (PK/BK)
^ circuit 687 (GY/YE)
^ circuit 16 (RD./LG)
^ ignition switch wiring CJB instrument cluster
Test Steps F1-F6:
Test Step F7:
PINPOINT TEST F: DTC B1360 - IGNITION ACC/RUN CIRCUIT OPEN