Cylinder Head Assembly: Testing and Inspection
11 12 729 Checking cylinder head for water leaks (N18)
Special tools required:
Necessary preliminary tasks:
- Remove cylinder head.
- Disassemble cylinder head.
Extend special tool 11 9 521 with special tool 11 9 523.
Installation note:
Construct the special tool 11 9 521 so that all water channels are sealed.
Secure special tool 11 9 523 to 25 Nm.
IMPORTANT: For the N18 engine, the special tool 11 9 522 must be modified.
Dimension (A) 15 mm, Dimension (B) 79.85 mm.
Both dimensions must be transferred to special tool 11 9 522 .
Separate the upper corner along the dotted line with a suitable tool.
Screw special tool 11 9 522 with the existing screws (1 and 3) of the coolant thermostat.
Sealing flange must rest flat.
NOTE:
Compressed air at valve (2) must not exceed 3 bar.
Heat cylinder head to 60 °.
Visual inspection in a water bath.
Picture shows (N12).
Assemble engine.