Required Operations
EMR-90-010 RECALL PROCEDURE SEQUENCE:
Flow chart which shows the general description of the REQUIRED OPERATIONS.
These "REQUIRED OPERATIONS" are as follows:
1. Clean the carburetor.
2. Test the Carburetor Feedback System. Replace the Oxygen Sensor and or the Jet Mixture Solenoid Valve as needed.
3. Remove the carburetor.
4. Install a Choke Shim.
5. Replace the Enrichment Solenoid Jet.
6. Remove and clean the Sub-EGR Valve.
7. Remove and clean the EGR Valve.
8. Reinstall the carburetor.
9. Install the Vacuum Control Valve and Vacuum Hose Assembly.
10. Affix the Service Label.