Charging System Preliminary Inspection
CHARGING SYSTEM PRELIMINARY INSPECTION
Inspection Procedure
1. CHECK BATTERY TERMINALS CONNECTION
Check if battery terminals are clean and tight.
Is the inspection result normal?
YES- GO TO 2.
NO- Repair battery terminals connection.
2. CHECK FUSE
Check for blown fuse and fusible link.
Is the inspection result normal?
YES- GO TO 3.
NO- Be sure to eliminate cause of malfunction before installing new fuse or fusible link.
3. CHECK GENERATOR GROUND TERMINAL CONNECTION
Verify connector E206 terminal 5 (generator ground harness) is clean and tight.
Is the inspection result normal?
YES- GO TO 4.
NO- Repair connection.
4. CHECK DRIVE BELT TENSION
Check drive belt tension. Procedures.
Is the inspection result normal?
YES- Inspection End.
NO- Repair as needed.