Operation CHARM: Car repair manuals for everyone.

Ignition Timing: Adjustments

PREPARATION
- Make sure that the following parts are in good order.
(1) Battery
(2) Ignition system
(3) Engine oil and coolant levels
(4) Fuses
(5) ECM harness connector
(6) Vacuum hoses
(7) Air intake system (Oil filler cap, oil level gauge, etc.)
(8) Fuel pressure
(9) Engine compression
(10) EGR valve operation
(11) Throttle valve
(12) Evaporative emission (EVAP) canister purge control valve
- On air conditioner equipped models, checks should be carried out while the air conditioner is "OFF".
- When checking idle speed, ignition timing and mixture ratio of A/T models, shift lever to "N" position.
- When measuring "CO" percentage, insert probe more than 40 cm (15.7 in) into tail pipe.
- Turn off headlamps, heater blower, rear window defogger.
- Keep front wheels pointed straight ahead.
- Make the check after the cooling fan has stopped.




OVERALL INSPECTION SEQUENCE FLOW CHART
















OVERALL INSPECTION SEQUENCE
- If a vehicle contains a part which is operating outside of design specifications with no MIL illumination, the part shall not be replaced prior to emission testing unless it is determined that the part has been tampered with or abused in such a way that the diagnostic system cannot reasonably be expected to detect the resulting malfunction.