With CONSULT
PRELIMINARY CHECK 3 - CRUISE TEST (WITH CONSULT)
- Using CONSULT, conduct a cruise test and record the result.
- Print the result and ensure that shifts and lock-ups take place as per "Shift Schedule."
CONSULT SETTING PROCEDURE
1. Turn off ignition switch.
2. Connect "CONSULT" to data link connector for CONSULT. (Data link connector for CONSULT is located behind the fuse box cover.)
3. Turn on ignition switch.
4. Touch "START".
5. Touch "A/T".
6. Touch "DATA MONITOR".
7. Touch "SETTING" to set recording condition.
8. Touch "LONG TIME" and "ENTER" key.
9. Go back to SELECT MONITOR ITEM and touch "MAIN SIGNALS".
10. Touch "START".
11. When performing cruise test, touch "RECORD".
12. After finishing cruise test part 1, touch "STOP".
13. Touch "DISPLAY".
14. Touch "PRINT".
15. Touch "PRINT" again.
16. Check the monitor data printed out.
17. Continue cruise test part 2 and 3.