BCM Power Supply and Ground Circuit Inspection
TRUNK LID OPENER
BCM Power Supply and Ground Circuit Inspection
1.CHECK FUSES AND FUSIBLE LINK
- Check 40A fusible link (letter g , located in the fuse and fusible link box).
- Check 10A fuses [No. 6, 8 and 20, located in the fuse block (J/B)].
OK or NG
OK - GO TO 2.
NG - If fuse is blown, be sure to eliminate cause of malfunction before installing new fuse. Description and Operation .
2.CHECK BCM POWER SUPPLY CIRCUIT
1. Turn ignition switch OFF.
2. Disconnect BCM.
3. Check voltage between BCM connectors and ground.
OK or NG
OK - GO TO 3.
NG - Repair or replace the harness.
3.CHECK GROUND CIRCUIT
Check continuity between BCM connector M20 terminal 67 and ground.
67 - Ground : Continuity should exist.
OK or NG
OK - Power supply and ground circuit is OK.
NG - Repair or replace harness.