Operation CHARM: Car repair manuals for everyone.

Road Test





Road Test

DESCRIPTION





- The purpose of the test is to determine overall performance of CVT and analyze causes of problems.
- The road test consists of the following three parts:
1. "Check Before Engine Is Started" SEE Check before Engine Is Started SEE Check at Idle .
2. "Check at Idle" SEE Check before Engine Is Started SEE Check at Idle .
3. "Cruise Test" SEE Cruise Test .





- Before road test, familiarize yourself with all test procedures and items to check.
- Perform tests on all items until specified symptom is found. Troubleshoot items which check out No Good after road test.

CONSULT-III START PROCEDURE
- Using CONSULT-III, perform a cruise test and record the result.
- Print the result and ensure that shifts and lock-ups take place as per Shift Schedule.
1. Touch "DATA MONITOR" on "SELECT DIAG MODE" screen.
2. Touch "MAIN SIGNALS" to set recording condition.
3. See "Numerical Display", "Bar chart Display" or "Line Graph Display".
4. Touch "START".
5. When performing cruise test. SEE Cruise Test .
6. After finishing cruise test part, touch "RECORD".
7. Touch "STORE".
8. Touch "BACK".
9. Touch "DISPLAY".
10. Touch "PRINT".
11. Check the monitor data printed out.