| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
Resurface/Grind |
Right Bank | 10.8 | 7.6 | A | Includes: R&R Cylinder Head, Grind All Valves & Seats And Mark All Necessary Adjustments. |
Left Bank | 10.8 | 7.9 | A | Includes: R&R Cylinder Head, Grind All Valves & Seats And Mark All Necessary Adjustments. |
Both Banks | 15.7 | 11.4 | A | Includes: R&R Cylinder Head, Grind All Valves & Seats And Mark All Necessary Adjustments. |
Add the Following Operations If Performed With Valves, Grind |
Valve Guides, Renew |
Each | 0.2 | 0.0 | A | |
Camshaft, Renew |
Right Bank |
One | 1.3 | 0.0 | A | |
Left Bank |
One | 1.2 | 0.0 | A | |
Tune-Up | 0.6 | 0.0 | A | |
Valve Guides, Ream |
Each | 0.2 | 0.0 | A | |
Lifters, Renew |
Right Bank | 1.9 | 0.0 | A | |
Left Bank | 1.9 | 0.0 | A | |
Both Banks | 2.7 | 0.0 | A | |
Timing Chain, Renew | 2.1 | 0.0 | A | |