Operation CHARM: Car repair manuals for everyone.

A/T - New Rocker-Joint Drive Link and Driven Sprocket

Bulletin Number: 93-7-23

Reference Number: 377107

Publish Date: 7/93

Subject:
NEW ROCKER-JOINT DRIVE LINK AND DRIVE/DRIVEN SPROCKET ASSEMBLY (INFORMATION)

Models Affected:
1993 BONNEVILLE AND GRAND PRIX MODELS WITH 4T60,4T60E TRANSMISSIONS

TRANSAXLE APPLICATIONS:
1993 HYDRA-MATIC 4T60 (RPO ME9) 1993 HYDRA-MATIC 4T60-E (RP0 M13)

TRANSAXLE MODELS:

3AVW, 3AWW, 3AZW, 3AMW, 3ANW, 3APW,
3ABW, 3BTW, 3CXW, 3CZW, 3PHW, 3CWW,
3WFH

SERVICE INF0RMATION: (FIGURES 1 AND 2)

A new Rocker-Joint Design Drive Link Assembly (510/507) has been
released for all 1993 HYDRA-MATIC 4T60 (RPO ME9) and select 1993
HYDRA-MATIC 4T60-E (RPO M13) transaxies.

Due to the unique Rocker-Joint drive link configuration, it was
necessary to change the tooth geometry on the drive and driven
sprockets.

NOTE:
A Rocker-Joint drive link assembly cannot be used on a transaxle that previously had a Round Pin drive link unless the drive and driven sprockets have been updated (or vice versa).

NOTE:
If a Rocker-Joint link is assembled on a unit without updating the drive and driven sprocket (or vice versa), wear on the sprockets and drive link will be greatly increased. Also, drive link noise may also increase to the level that may be considered unacceptable.

Rocker-Joint Advantages Over Round Pin Drive Link Design

* Low friction of design permits smoother operation at high speeds.

* Reduced chain wear.

* Higher efficiency at continuous speeds.








DATE OF PRODUCTION CHANGE: (Figure 1 and 2)

The new Rocker-Joint design was implemented into production on December 21, 1992 (Julian Date 356).

Drive/Driven Sprocket Implementation Date
37/33 Sprocket Ratio - December 21, 1992
33/37 Sprocket Ratio - December 21, 1992

35/35 Sprocket Ratio - may be implemented mid-year 1994





IDENTIFICATION OF PARTS: (Figure 3)





Identification of new parts:

SERVICE PART INFORMATION:








SERVICE MANUAL INFORMATION:

Refer to the appropriate service manual section, Automatic Transaxle On-Vehicle Section 7A for proper on vehicle service to remove and replace a 4T60/4T60-E transaxle. Refer to Automatic Transaxle Unit Repair Section for proper disassemble and assemble procedures.

LABOR TIME INFORMATION:

Labor time should be charged under Operation Number K-7520 for "Link Assembly, Transaxle Drive - Replace":

INC: Cooler line flush, oil pressure test, clean and inspect parts and all necessary measurements and adjustments.

NOTE:
For check and adjust toe-in, refer to operation E2OOO and add the applicable times to the regular hours column. Applies to W series only.