REMOVAL PROCEDURE1. Disconnect the negative battery cable.
2. Remove the drive belt from the generator.
3. Place the coolant recovery reservoir aside for access. Refer to Coolant Recovery Reservoir Replacement in Cooling System.
4. Remove the generator rear brace nut (4).
5. Remove the bolts (1, 2, 3) from the generator.
6. Disconnect the electrical connector from the generator.
7. Remove the protective boot from the generator output BAT terminal.
8. Remove the generator output BAT terminal nut and remove the positive battery lead from the generator.
9. Remove the generator.
INSTALLATION PROCEDURE
1. Position the generator to the engine.
2. Install the positive battery lead to the generator.
NOTE: Refer to Fastener Notice in Service Precautions.
3. Install the generator output BAT terminal nut.
Tighten
Tighten the generator output BAT terminal nut to 20 N.m (15 lb ft).
4. Install protective boot to the generator output BAT terminal.
5. Connect the electrical connector to the generator.
6. Install the generator bolts (2, 3) to the generator.
IMPORTANT: Do not tighten the bolts.
7. Install the generator pivot bolt (1) to the generator.
IMPORTANT: Do not tighten the bolt.
8. Tighten the generator bolts in the order described. The following is a mandatory torque sequence:
Tighten
1. Tighten the generator pivot bolt (1) to 50 N.m (37 lb ft).
2. Tighten the generator bolt (2) to 50 N.m (37 lb ft).
3. Tighten the generator bolt (3) to 50 N.m (37 lb ft).
4. Install the generator rear brace nut (4).
Tighten
Tighten the nut to 25 N.m (18 lb ft).
5. Install the coolant recovery reservoir.
6. Install the drive belt.
7. Connect the negative battery cable.