Heating and Air Conditioning: Service and Repair
Assembly Work On The Air-conditioning System
Service unit SECU 134
NOTE: The manufacturer's operating and repair instruc-tions must be observed when carrying out all work on the service unit.
Assembly work involving the refrigerant system
During all work on the air-conditioning system which necessitates opening the refrigerant system, the system contents must first be disposed of correctly. When doing so, follow the safety regulations.
Dirt and moisture must be kept out of the air-conditioning system's pipe system. Thorough cleanliness must therefore be ensured during all work. System components must never be cleaned on the inside with hot steam. Use only nitrogen for cleaning purposes.
When replacing a component, all openings must be closed off with suitable plugs.
General assembly sequence
1. Remove refrigerant by suction.
2. Remove faulty part.
3. Evacuate.
4. Check the system for leaks.
5. Rinse with refrigerant.
6. Empty the system by suction again.
7. Evacuate.
8. Fill.
NOTE: Pay attention to sealing rings when disconnecting or connecting the hose connections.
The charging valves are located in the area of the front right spring strut.
Removing refrigerant by suction and cleaning
Cleaning the refrigerant
Draining off old refrigerant oil
Evacuating
Topping up with new refrigerant oil
Filling via the high-pressure side
After using the SECU, perform internal suction removal; first close the hand valves on both suction lines.
Refilling the air-conditioning system
NOTE: In the event of insufficient refrigeration performance, remove the refrigerant by suction, top up with the stipulated quantity and check the system for leaks.
1. Remove the refrigerant by suction using the service unit.
2. Determine the refrigerant oil quantity after the refrigerant has been removed by suction.
3. Fill up with new refrigerant oil.
4. Evacuate.
5. Fill with the stipulated amount of refrigerant.
6. Check the system for leaks.