9902519 Removing and installing instrument cluster


WM 902519 Removing and installing instrument cluster

Technical values





Removing instrument cluster

Overview





Removing instrument cluster

Remove left dashboard cover -> 701619 Removing and installing dashboard cover - section on "Removing" 70161902 Removing and Installing Dashboard Cover on the Passenger's Side.

Switch off ignition and remove ignition key.
1. Use a plastic spatula to unclip the trim from the upper cover at the left and right.





2. Unscrew both fastening screws -1- for the dashboard insert (cover for instrument cluster).





3. Unscrew fastening screws for the instrument cluster -2-.
4. Press in the dashboard inset (cover for instrument cluster) at the sides in order to unclip it -arrows A-.
4.1. Lift it slightly at the front -arrow B -.
4.2. Unscrew fastening screw -3-.
5. First pull the dashboard insert (cover for instrument cluster) -b- to the rear -arrow A- , then remove it by pulling it upwards -arrow B-.





6. Lift up the instrument cluster, pull it forward and fold it forward.





7. Release the lock -arrow- and pull off the connectors -A-.
8. Remove instrument cluster.

Installing instrument cluster

1. Position instrument cluster, then push on connector -A- and lock it -B- until it engages securely.





2. Fold back instrument cluster and position it in instrument panel.
3. Place dashboard insert (cover for instrument cluster) -b- in the installation position -arrow-.





4. Lift dashboard insert (cover for instrument cluster) slightly at the front -arrow A- and insert the fastening screw -3- but do not tighten it.





5. Push dashboard insert (cover for instrument cluster) completely to the front -arrows B- and tighten the fastening screw -3-.
6. Press dashboard insert (cover for instrument cluster) downwards and secure it with the fastening screws -1 and 2-.=> Tightening torque: 1.4 Nm (1.0 ftlb.) => Tightening torque: 1.4 Nm (1.0 ftlb.).
7. Insert trim panel and press it against the dashboard insert (cover for instrument cluster) at the top until the clips engage securely.





Install left dashboard cover. -> 70161901 Removing and installing dashboard cover on driver's side - section on "Installing" 70161901 Removing and installing dashboard cover on the driver's side.

Programming instrument cluster

Information

- In the instrument cluster is also the gateway control unit. When replacing the instrument cluster, the values read out in the Instrument cluster menu must also be written in the gateway control unit. See description of the procedure.

- If the control unit is replaced, it must be programmed and coded using the Porsche System Tester. This is to adapt the control unit to the vehicle and equipment.

- If possible, before the control unit is removed and replaced, a read-out of the vehicle data should be obtained using the Porsche System Tester.

- During coding, it is essential to guarantee the power supply for the Porsche System Tester. It is essential to connect a battery charger with a current rating of at least 40 A to the vehicle battery.

- Symbol for the Tab key = =>|

- The Porsche System Tester instructions take precedence and in the event of a discrepancy these are the instructions that must be followed. Deviations may occur with later software versions.

- The procedure described here has been structured in general terms; different texts or additions may appear in the Porsche System Tester.

1. Connect the Porsche System Tester to the vehicle and start the System Tester. Switch on ignition and press >> to continue.
2. Select vehicle type.
3. Switch from the vehicle type to the list of control units.
4. Select Instrument cluster with the cursor keys and press >>.
5. Select Control unit replacement with the cursor keys and press >>.
6. Select Read out values (codings) with the cursor keys and press >>.
7. The message Coding read-out complete will appear on the Porsche System Tester screen. Press >>.
8. Switch off ignition and replace instrument cluster => Removing instrument cluster
9. Switch on ignition. After replacing the control unit, the data that was read out will be installed when you select the Write values menu (see Step 6). Press >>.
10. System Tester displays Coding write-in complete. Press >>.
11. Follow the instructions on the Tester.
12. Go back to the control unit overview and select Gateway control unit.
13. In the Control unit replacement menu, press >> to continue.
14. The data that was read out will be installed when you select the Write values menu (see Step 6). Press >>.
15. System Tester displays Coding write-in complete. Press >>.
16. Exit the menu, switch off ignition, lock and unlock the vehicle and read out the fault memory.