2ZR-FE ENGINE MECHANICAL: ENGINE UNIT: INSTALLATION
1. INSTALL WIRE HARNESS CLAMP BRACKET
(a) Install the 4 wire harness clamp brackets with the 4 bolts.
Torque : 10 Nm (102 kgf-cm, 7 ft-lbf) for bolt A
Torque : 13 Nm (130 kgf-cm, 9 ft-lbf) for bolt B
2. INSTALL EXHAUST MANIFOLD
(a) Install a new exhaust manifold gasket and exhaust manifold with the 5 nuts in the sequence shown in the illustration.
Torque : 21 Nm (214 kgf-cm, 16 ft-lbf) for Type A
Torque : 37 Nm (377 kgf-cm, 27 ft-lbf) for Type B
Text in Illustration
3. INSTALL MANIFOLD STAY
(a) Install the manifold stay with the 3 bolts.
Torque : 43 Nm (438 kgf-cm, 32 ft-lbf)
4. INSTALL NO. 1 EXHAUST MANIFOLD HEAT INSULATOR
(a) Install the No. 1 exhaust manifold heat insulator with the 4 bolts.
Torque : 12 Nm (122 kgf-cm, 9 ft-lbf)
5. INSTALL AIR TUBE ASSEMBLY
(a) Install the air tube assembly with the 2 bolts.
Torque : 10 Nm (102 kgf-cm, 7 ft-lbf)
6. INSTALL NO. 1 WATER BY-PASS PIPE
(a) Install the water by-pass pipe with the 2 bolts.
Torque : 21 Nm (214 kgf-cm, 16 ft-lbf)
(b) Connect the No. 3 water by-pass hose with the clip.
7. INSTALL WATER INLET HOSE
(a) Install the water inlet hose with the 2 clips.
8. INSTALL WATER BY-PASS HOSE
(a) Install the water by-pass hose with the clip.
9. INSTALL OIL LEVEL GAGE GUIDE
(a) Install a new O-ring.
(b) Install the oil level gage guide with the bolt.
Torque : 21 Nm (214 kgf-cm, 16 ft-lbf)
10. INSTALL OIL LEVEL DIPSTICK
11. INSTALL VENTILATION HOSE
(a) Install the ventilation hose.
12. INSTALL FAN BELT ADJUSTING BAR
(a) Install the fan belt adjusting bar with the bolt.
Torque : 19 Nm (189 kgf-cm, 14 ft-lbf)
13. INSTALL GENERATOR ASSEMBLY Installation
14. INSTALL FUEL INJECTOR Installation
15. INSTALL INJECTOR VIBRATION INSULATOR Installation
16. INSTALL NO. 1 DELIVERY PIPE SPACER Installation
17. INSTALL FUEL DELIVERY PIPE SUB-ASSEMBLY
(a) Install the fuel delivery pipe with the 4 fuel injectors, then provisionally install the 3 bolts.
NOTICE:
* Do not drop the fuel injectors when installing the fuel delivery pipe.
* Check that the fuel injectors rotate smoothly after installing the fuel delivery pipe.
(b) Tighten the 3 bolts to the specified torque.
Torque : 21 Nm (214 kgf-cm, 16 ft-lbf)
18. INSTALL INTAKE MANIFOLD
(a) Install a new gasket onto the intake manifold.
(b) Provisionally tighten the intake manifold and manifold stay with the 4 bolts and 2 nuts in the order shown in the illustration, and then tighten them to the specified torque.
Torque : 28 Nm (286 kgf-cm, 21 ft-lbf)
(c) Install the wire harness clamp onto the intake manifold.
(d) Install the ventilation hose into the intake manifold.
(e) Install the No. 1 vacuum transmitting hose with the clip.
(f) Install the No. 1 fuel vapor feed hose into the throttle body manifold.
(g) Install the 2 water by-pass hoses with the 2 clips.
19. INSTALL NO. 1 RADIATOR HOSE
(a) Install the No. 1 radiator hose with the clip.
20. INSTALL HEATER WATER HOSE INLET A
(a) Install heater water inlet hose A with the clip.
21. INSTALL HEATER WATER OUTLET HOSE A (FROM HEATER UNIT)
(a) Install heater water outlet hose A with the clip.
22. INSTALL NO. 2 VENTILATION HOSE
(a) Install the No. 2 ventilation hose.
23. INSTALL ENGINE WIRE
24. INSTALL RADIO SETTING CONDENSER
(a) Install the radio setting condenser with the bolt.
Torque : 10 Nm (102 kgf-cm, 7 ft-lbf)
(b) Connect the radio setting condenser connector.
25. INSTALL IGNITION COIL ASSEMBLY
(a) Install the 4 ignition coil assemblies with the 4 bolts.
Torque : 10 Nm (102 kgf-cm, 7 ft-lbf)
(b) Connect the 4 ignition coil assembly connectors.