| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
Replace |
Complete Assembly Without Transfer Of Parts | 5.2 | 3.7 | B | Does Not Include: Transfer Of Any Part Of Engine Or Replacement Of Optional Equipment. |
NOTE |
With AC, Add | 0.4 | 0.0 | B | |
Complete Assembly With Transfer Of Parts | 7.5 | 0.0 | B | Includes: Transfer Of All Fuel & Electrical Units. Does Not Include Transfer Of Optional Equipment. |
NOTE |
With AC, Add | 0.4 | 0.2 | B | |
Short Block | 12.5 | 8.1 | A | Includes: R&I Engine And Transfer All Necessary Components. |
NOTE |
With AC, Add | 0.4 | 0.2 | A | |
Long Block | 10.5 | 0.0 | A | Includes: R&I Engine And Transfer All Necessary Components Not Supplied With Long Block. |
NOTE |
With AC, Add | 0.4 | 0.0 | A | |
Overhaul/Rebuild | 20.4 | 10.1 | A | Includes: Disassemble & Clean Engine, Ridge Ream & Hone Cylinders. Inspect & Replace All Necessary Components, R&I Engine, Grind Valves And Tune-Up. |
NOTE |
With AC, Add | 0.4 | 0.2 | A | |