Combination Valve, Checking
Combination valves, checking
Recommended special tools and equipment
- VAG1390 Hand Vacuum Pump
Test requirements
- No leaks in vacuum lines or hose connections.
- Vacuum hoses not clogged or kinked
- Pressure hose for Secondary Air Injection (AIR) Pump Motor not clogged or kinked
Test sequence
- Disconnect vacuum hose of combination valve to be checked:
- Cylinder bank 1, item 3 ,
- Cylinder bank 2, item 4 .
NOTE:
- Cylinder bank 1 = in driving direction, right
- Cylinder bank 2 = in driving direction, left
- Connect hand vacuum pump to vacuum connection of combination valve (arrow).
NOTE: Do not use pressurized air for the following test!
- Remove front noise insulation.
- Disconnect pressure hose (arrow) between Secondary Air Injection (AIR) Pump Motor and connecting line and blow into it with light pressure.
Both combination valves must be closed.
NOTE: To disengage, compress the buttons at the hose coupling.
- Operate hand vacuum pump.
The respective combination valve must open.
If the combination valve does not open or it is constantly open:
- Replace the respective combination valve:
- Cylinder bank 1, item 3 ,
- Cylinder bank 2, item 4 .
- Erase DTC memory of Engine Control Module (ECM), Diagnostic mode 4: Reset/erase diagnostic data.
- Generate readiness code. Monitors, Trips, Drive Cycles and Readiness Codes