Engine Installing
Engine, Installing
CAUTION!
When doing any repair work, especially in the engine compartment, pay attention to the following due to clearance issues:
• Route lines of all types (e.g. for fuel, hydraulic, additive, coolant and refrigerant, brake fluid, vacuum) and electrical wiring so that the original path is followed.
• To prevent damages to the lines, make sure there is sufficient clearance to all moving or hot components.
Installation is performed in reverse order. When doing this note the following:
- Make sure centering sleeves for engine to transmission are installed in cylinder block. Install if necessary.
- Reconnect all lines, hoses and connections that were disconnected for the removal sequence.
- Electrical connections and routing.
- Connect Air Conditioning (A/C) lines.
- Top off oil level for power steering system.
- Fill the cooling system. Refer to --> [ Cooling System, Draining and Filling ] [1][2][3]Cooling System, Draining and Filling.
- Check headlight adjustment, correct if necessary.
- Perform test drive and check all Diagnostic Trouble Code (DTC) memories. Refer to VAS 5052 "Guided Fault Finding".
Tightening Specifications