Timing Components: Adjustments
Valve Timing, Checking
Special tools, testers and auxiliary items required
• Counterhold Tool Touareg V10 (T10172)
• Guide Pins (T10193) for cylinder bank 1
• Guide Pins (T10194) for cylinder bank 2
Procedure
- Remove the noise insulation (=> [ (Item 14) Noise Insulation ] Description and Operation) and covers (=> [ (Item 13) Cover ] Description and Operation) from the cylinder heads.
- Rotate the crankshaft slowly in engine rotation direction using the counterhold tool Touareg V10 (T10172) until the guide pin (T10193) for the camshaft for cylinder bank 1 and the guide pin (T10194) for the camshaft for cylinder bank 2 can be installed into the fitting holes as shown.
- Raise the vehicle on the hoist.
- Check whether the mark - arrow A - on the vibration damper aligns with the alignment pin - arrow B -.
If the marks do not align:
- Adjust the valve timing. Refer to => [ Valve Timing, Adjusting ] Adjustments.