Operation CHARM: Car repair manuals for everyone.

Intercooler: Testing and Inspection






Charge Air System, Checking for Leaks

Special tools, testers and auxiliary items required

Adapter (V.A.G 1687/5)

Testing Unit for Turbocharger (V.A.G 1687)

Ultrasonic Measuring Device (V.A.G 1842)

Test Sequence:

- Remove the noise insulation.

- Release the securing clamp - A - and disconnect the hose - B - from the charge air pipe.






- Connect the adapter (V.A.G 1687/5) to the charge air hose - A - and rotate it around approximately 90° - B -.






Prepare the testing unit for turbocharger (V.A.G 1687) as follows:






- Turn the pressure regulator valve - 2 - counterclockwise until it stops.

- Close the valves - 3 and 4 -.

In order to be able to turn the pressure regulator valve - 2 -, the rotary knob must be pulled upward.

- Connect the testing unit for turbocharger (V.A.G 1687) as shown.






- Connect the compressed air line - 1 - (pressurized air supply) to the testing unit for turbocharger (V.A.G 1687).






If water is located in the viewing glass, drain it via water the drain plug - 6 -.

- Open the valve - 3 -.

- Set the pressure to 0.5 bar using pressure the regulator valve - 2 -.


The pressure must not exceed 0.5 bar! A pressure set too high may damage the engine.

- Open the valve - 4 - and wait until the testing circuit has filled. If necessary, continue to regulate pressure to 0.5 bar.

- Check the charge air system for poorly sealed areas by listening, feeling, using commercially available leak detection spray or by using the ultrasonic measuring device (V.A.G 1842).

Charge air hose connecting and disconnecting, Refer to => [ Charge Air Hose and Pipe, Disconnecting and Connecting ] Charge Air Hose and Pipe, Disconnecting and Connecting.

A small quantity of air dissipates via the valves in the engine. A pressure retention test is not possible for this reason.

Handling instructions for the ultrasonic measuring device (V.A.G 1842). Refer to the tools operating manual.

Before removing the adapter, discharge the pressure in the testing circuit by pulling off the coupling from the adapter (V.A.G 1687/5).

Hose connections and charge air system hoses must be free of oil and grease before installing.