Pressure Regulator Valves, Checking



Pressure Regulator Valves, Checking

NOTE: The Automatic Transmission Pressure Regulating Valve 1 N215 , Automatic Transmission Pressure Regulating Valve 2 N216 , Automatic Transmission Pressure Regulating Valve 3 N217 , Automatic Transmission Pressure Regulating Valve 4 N218 , Automatic Transmission Pressure Regulating Valve 5 N233 , and the Automatic Transmission Pressure Regulating Valve 6 N371 are components of the Mechatronic unit in the transmission.

Requirements
- The battery voltage must be at least 12.5 Volts.
- All electrical consumers must be switched off.
- The parking brake must be engaged.
- The elector lever must be in the "P" position.
- The Ground (GND) connections to transmission must be OK.







Test sequence
- Disconnect the electrical connector in the - direction of the arrow - and remove it from the Transmission Control Module (TCM) J217.
- Observe safety precautions.
- Check the electrical harness connector for contact corrosion and ingress of water.

If the electrical harness connector is not OK:
- Repair the malfunction.

If the electrical harness connector is OK:
- Check the wiring according to the wiring diagram:

If no malfunctions are found in the wiring:
- Replace the Mechatronic unit in the transmission.

NOTE: The Automatic Transmission Pressure Regulating Valve 1 N215 , Automatic Transmission Pressure Regulating Valve 2 N216 , Automatic Transmission Pressure Regulating Valve 3 N217 , Automatic Transmission Pressure Regulating Valve 4 N218 , Automatic Transmission Pressure Regulating Valve 5 N233 , and the Automatic Transmission Pressure Regulating Valve 6 N371 are components of the Mechatronic unit in the transmission and cannot be replaced separately.

Final procedures
1. Check the DTC memory.
2. If necessary, erase DTC memory of the Transmission Control Module (TCM) J217.
3. Generate readiness code.